Project Name
AACO Oakey SAFF® PFAS remediation Water Treatment Plant (WTP)
Project Location
Oakey QLD
Division
Enviro
End User
Client
Department of Defence
OPEC Project Manager
Jonathon Heffer
Contract Value
$7.2M
Year Completed
TBC
SCOPE SUMMARY
Project Description
Design, build, test, and commission a SAFF® PFAS remediation WTP capable of processing a minimum of 250,000 L/day of PFAS contaminated water to below the Health Based guidance Values (HGBV’s) in the contract.
OPEC Scope
OPEC was engaged to develop, design, build, test, and commission a SAFF® WTP that could process a minimum of 250,000 L/day to below the HGBV’s in the contract.
Challenges / Solutions
SAFF® was invented by OPEC. Taking a lab-based invention / technology and developing it into a working full scale PFAS remediation WTP.
Innovations
Concept of SAFF® is an OPEC Innovation, allowing PFAS remediation and high level of concentration of waste product, without the need of high quantities adsorbents